Permitting & Development Friction Index

Aggregated via DuckDB from official municipal open-data permit portals (2021-2026 YTD). Categories with fewer than 30 permits suppress median/P75 cycle days (`insufficient_sample: true`). Annual trend deltas exclude partial-year 2026.

Compare Pilot Cities →
Not Directly Comparable Across Cities — Different Permit Milestones: Not directly comparable across cities: Raleigh measures application-to-issuance days (applieddate -> issueddate), whereas Minneapolis CCS measures issue-to-completion days (issueDate -> completeDate) and is right-censored in recent years.

Pilot Jurisdiction Permit Turnaround Profiles

Each pilot reflects its own portal milestone definition; multi-year deltas compare complete calendar years only (excluding 2026 YTD).

2021-2026 (2026 YTD)Independent Metric

Raleigh, NC

Days to Issue (Applied -> Issued)

37.2d
P75: 71.1 days

Measures elapsed calendar days from building permit application (`applieddate`) to permit issuance (`issueddate`). Includes commercial, residential new construction, and residential remodels; standalone trade permits are largely excluded from this layer.

Total Permits
33,479
Construction Value
$13.45B
Fee / Valuation
1.08%
Complete-Year Cycle Trend (2021–2025)+42.9%
2021: 28d2022: 38d2023: 42d2024: 40d2025: 40d2026 (YTD): 36d
2021-2026 (2026 YTD)Independent Metric

Minneapolis, MN

Days to Complete (Issue -> Complete)

123.0d
P75: 340.0 days

Measures elapsed calendar days from permit issuance (`issueDate`) to inspection completion (`completeDate`). Because open permits without a `completeDate` are excluded from completion medians, recent years (2025–2026) are right-censored toward faster-completing jobs.

Censoring Caveat: Right-censored metric: only permits with a recorded completion date are included in cycle-day medians, biasing 2025–2026 downward.

Total Permits
242,708
Construction Value
$20.04B
Fee / Valuation
1.54%
Complete-Year Cycle Trend (2021–2025)-60.4%
2021: 169d2022: 248d2023: 179d2024: 114d2025: 67d2026 (YTD): 30d

Raleigh, NC — Turnaround & Fees by Permit Type

Days to Issue (Applied -> Issued)

Fee Ratio: 1.08%
CategoryCountMedianP75Fee %
Residential Remodel / Addition
16,33720.1d41.4d1.17%
Commercial Remodel / Upfit
8,59855.1d110.3d1.01%
New Residential
7,88855.8d81.1d1.47%
New Commercial / Multifamily
65571.5d141.0d0.45%
Trade (Plumbing / Mechanical / Electrical)
Insufficient sample (n=1 < 30); median and P75 cycle days suppressed.
1———

Minneapolis, MN — Turnaround & Fees by Permit Type

Days to Complete (Issue -> Complete)

Fee Ratio: 1.54%
CategoryCountMedianP75Fee %
Trade (Plumbing / Mechanical / Electrical)
146,457125.0d341.0d3.40%
Residential Remodel / Addition
71,06593.0d238.0d2.49%
Commercial Remodel / Upfit
24,464239.0d490.0d1.11%
New Residential
431355.0d608.0d1.91%
New Commercial / Multifamily
291612.5d916.0d2.22%